Construction Progress
Ground Breaking Ceremony June 25, 2008
We did not do this all by hand, even though it was an enthusiastic gathering
Footings begin to be poured July 16, 2008
Getting ready to pour the walls July 22. 2008
The basement walls poured July 30, 2008 Elevator Shaft being built August 20, 2008 Up go the steel beams and posts August 25, 2008 Now comes the floor August 26, 2008 It's not just a hole in the ground anymore
Water and sewer lines are put in while the client line spills out of the old pantry door
|